Short answer: Toronto homeowners applied for 185 garden suite building permits from January to October 2026, up from 102 in the same months of 2025, an increase of 81%. The typical permit issued in 2026 took 73 days from application to approval. About one in six garden suite applications since 2022 was refused or cancelled.
We pulled every building permit the City of Toronto publishes on its open data portal and counted the projects whose permit describes a garden suite or a laneway suite. Here is what that shows, and what it means if you are planning one.
Garden suite applications by year
| Year applied | Garden suites | Laneway suites |
|---|---|---|
| 2022 | 19 | 47 |
| 2023 | 40 | 30 |
| 2024 | 79 | 33 |
| 2025 | 122 | 48 |
| 2026 (to Nov 6) | 189 | 39 |
Garden suites have been allowed city-wide since 2022, and applications have grown every year. Laneway suites, allowed since 2018, have stayed roughly flat at 30 to 50 a year. That makes sense: only lots that back onto a public lane can build a laneway suite, while most houses with a real backyard can build a garden suite.
Where they are being built
Garden suite projects since 2017, by postal district:
| Postal district | Area | Garden suites | Laneway suites |
|---|---|---|---|
| M6 | West end and York | 119 | 158 |
| M1 | Scarborough | 94 | 5 |
| M2 and M3 | North York | 82 | 2 |
| M8 and M9 | Etobicoke and the northwest | 71 | 3 |
| M4 | East end, East York, midtown | 64 | 53 |
| M5 | Downtown and central | 15 | 24 |
Laneway suites cluster in the older west and east ends, where the laneways are. Garden suites are spread across the whole city. Scarborough is second only to the west end, likely because its lots are deep and few of them back onto a lane. In 2026, Scarborough accounted for 32 garden suite applications, more than North York or Etobicoke.
How long a garden suite permit takes
Measured from the date the application was filed to the date the permit was issued:
- Garden suites issued in 2026: median 73 days (2025: 90 days, 2024: 76 days)
- Laneway suites issued in 2026: median 64 days (2025: about 100 days)
- One in four garden suite permits since 2017 took more than about 4.5 months
The clock starts when the City accepts a complete application. Design and engineering come before that, and usually take one to three months. So from first drawing to permit in hand, plan on roughly four to six months. Applications slow down when the City sends an examiner’s notice asking for changes to the drawings, and each round of changes adds weeks.
How many get refused or cancelled
Of the 451 garden suite projects in the data, 71 (about 16%) were refused, cancelled or pending cancellation. The data does not say why. In our experience the common causes are a lot that does not meet the zoning (not enough distance from the house, no 1 m fire access path, a protected tree in the way) or an owner who changed plans after seeing the full cost. Both are cheaper to find out before you pay for drawings. Our free lot check runs your address against the same City zoning and parcel data.
What owners declare as the construction value
Every permit lists an estimated construction value. For garden suites the median is $200,000, and for laneway suites $300,000. Half of garden suite permits fall between $100,000 and $400,000. Treat these as rough: owners and builders fill them in at application, before the final price is known, and they usually leave out design, City fees and servicing. For real all-in numbers, see how much a garden suite costs in Toronto.
What this means if you are planning one
- You are not early anymore. Applications nearly doubled this year.
- Permits are faster than most people think. About 2.5 months at the City for a clean application. Complete drawings that already meet the by-law are what keep it there.
- Check the lot first. One project in six never gets built, and the cheapest time to find a problem is before design starts.
The rules themselves, in plain English: Toronto garden suite rules, 2026.
Frequently asked questions
How many garden suites are there in Toronto?
The City’s permit data shows 449 garden suite projects applied for from 2022 to early November 2026, and 197 laneway suites in the same period. Not every one has been built yet: many are still under review, in construction, or were cancelled.
How long does it take to get a garden suite permit in Toronto?
For permits issued in 2026, the median was 73 days from application to issue. Add one to three months of design and engineering before you apply.
Do garden suite permits get refused in Toronto?
Yes, about 16% of the garden suite projects in the City’s data were refused or cancelled. Checking the lot against the zoning before design catches zoning problems before you pay for drawings.
Which part of Toronto has the most garden suites?
The west end and York (postal district M6), followed by Scarborough (M1) and North York (M2 and M3).
Method: City of Toronto Open Data, “Building Permits – Active Permits” and “Building Permits – Cleared Permits since 2017”, downloaded November 8, 2026. We counted building permits (not mechanical, plumbing or drain permits) whose description or structure type names a garden suite or a laneway suite, one project per address. Some projects may be described differently on their permit, so the real totals may be slightly higher. Postal districts are approximate area labels. Analysis by Kasa Suites.